Shenyang Railway Bureau Xinmin Project 60,418 square meters
Shenyang Railway Bureau Xinxin Project 60418 square meters 2700KW/10kV occupies: 200 square meters. Demolition of old boiler from April 1 to April 5. Civil foundation construction from April 1 to May 10. Heat storage body installation from May 10 to May 22. Insulation installation from May 23 to May 28. Electric resistance wire installation from May 25 to May 30. Fan heat exchanger installation from May 8 to June 3. Electrical installation from May 28 to June 5. Shell installation from May 29 to June 4. Waterway installation from May 29 to June 7. Central heating for the train station construction period: 68 days.
- Commodity name: Shenyang Railway Bureau Xinmin Project 60,418 square meters
Classification:
Key words:
Product Details
- 产品描述
-
Shenyang Railway Bureau Xinmin Project 60,418 square meters
2700KW/10kV Occupying area: 200 square meters
Demolition of old boiler from April 1 to April 5
Civil foundation construction from April 1 to May 10
Heat storage body installation from May 10 to May 22
Insulation installation from May 23 to May 28
Resistance wire installation from May 25 to May 30
Fan heat exchanger installation from May 8 to June 3
Electrical installation from May 28 to June 5
Shell installation from May 29 to June 4
Waterway installation from May 29 to June 7
Central heating at the train station, construction period: 68 days