Completion Record, Wulat Power Plant Heat Network Condenser Successfully Completed and Accepted
Release time:
2019-10-25
On October 20, Shandong Beichen was responsible for the successful completion and acceptance of the heat network condenser equipment of China Huaneng Wulat Power Plant's high back pressure renovation project. The construction team of 13 people lasted 40 days, overcoming difficulties such as cross-operation of on-site construction and completing the task with high quality, which was highly affirmed by the owner.
Heat transfer area of heat network condenser in this project7000 square metersDuring the implementation of the project, the company has fully communicated and cooperated with the on-site construction personnel to solve the difficult problems in the project construction, further clarify the time node, focus on solving the outstanding problems, speed up the progress and ensure the completion of the task on schedule.
We are grateful for the active cooperation of the owners and the efforts of the on-site construction personnel, and promise to fulfill the responsibilities and obligations of quality warranty, so that customers can feel at ease and rest assured.